Wood Vale improvements

Programme and next steps

  • outline design and consultation - September to December 2019 - completed
  • decision making and detailed design - January to August 2020 - completed
  • implementation of footway maintenance - January 2021 to September 2021 - completed
  • statutory consultation for waiting restrictions (double yellow lines) around priority working islands - November 2021 - completed
  • implementation of traffic islands and resurfacing - August 2022 - completed
  • monitoring – September 2022 onwards