Timeline / Programme

  • Consultation – September to October 2021 - Completed
  • Detailed Design – October to March 2022 - Completed
  • Construction – May 2022 - Completed
  • Monitoring – May 2022 to September 2023 - Ongoing
  • Consultation for trial scheme – 24 October to 20 November 2022
  • consultation for continuation of Cycle Route - 2023