Dog Kennel Hill bus lane widening

Project updates

Implementation of the proposals (subject to Statutory Consultation) was approved by the Cabinet Member in November 2019.

Following the end of the statutory consultation period, works will be carried out according to the construction programme below.

Construction programme

  • start date - 26 May 2020
  • duration - approximately 12 to 14 weeks

Traffic management for the works will involve lane closures and suspension of the bus lane. Residential access will be maintained at all times and parking restrictions and suspension will be in place around the works area.

Residents have been notified of the start of the works with contact details provided for any issues or queries regarding the execution of the works.

Page last updated: 24 March 2022

}

Privacy settings