Our local highways maintenance report

Information about the condition of our roads, how much we spend on maintenance and our planned maintenance in the future.

Our highways maintenance plans

Overall strategy

Our current approach to asset management and highway maintenance

As well as doing small patching work to make highways and footways safe, we also do planned resurfacing work. For this, we try to use a risk-based approach to follow the Well-managed Highway Infrastructure: A Code of Practice.

We do detailed inspections of our roads and footways every year. The information is then loaded into our computer software along with information about our priorities and budgets. The software then:

  • simulates how roads might deteriorate
  • advises what the best treatment might be
  • advises what it might cost
  • suggests when the work should be done

This helps us put together our planned programme of maintenance work.

How we follow best practice and deliver innovation

We work with other London councils and highways authorities across the county to keep up to date with best practice and innovation. We are also part of different professional groups including:

  • London Highway Engineering Group (LoHEG)
  • London Bridge Engineering Group (LoBEG)
  • Local Government Technical Advice Group (LGTAG) 

We also participate in annual National Highways and Transportation (NHT) survey, where Southwark residents rate their overall highway performance as the best in the country. 

Specific plans for 2025 to 2026

In 2025 to 2026 we anticipate spending two and a half times more on preventative works than reactive works. Approximately 71% of our spend will be on preventative works. 

In 2025 to 2026 we plan to:

  • resurface approximately 1.7 miles of carriageway
  • improve 70 footway sections in 42 streets
  • repair Rope Street bridge, Lavender Lock bridge and South Street bridge
  • repair Russia Dock footbridge, St James retaining wall and monuments in our cemeteries (with funding from our parks team)

We also estimate estimate we will fill 2,450 potholes, based on a projection of the last 5 years’ figures. 

Proposed highways maintenance programme for 2025 to 2026 
Budget year Road class Road Ward Treatment length (metres) Treated length (%) Section description Treatment description Cost Cumulative cost
2025 A2216 Lordship Lane Goose Green 128 25% Melbourne Grove to East Dulwich Grove Renewal  £448,694.61 £448,694.61
2025 A2208 Rotherhithe New Rd North Bermondsey 219 99% Raymouth Road to Hawkstone Road roundabout Structural surface  £371,388.76 £820,083.37
2025 A2199 College Road Dulwich Wood 106 100% Fountain Drive to Kingswood Drive Asphalt preservation  £48,530.93 £868,614.30
2025 A2215 Hanover Park Rye Lane 119 42% Clayton Road to Rye Lane Structural surface  £170,382.48 £1,038,996.78
2025 B240 Harper Road Chaucer 592 90% Falmouth Road to New Kent Road Thin surface  £515,138.30 £1,554,135.08
2025 U0331/005 Bidwell Street Nunhead Queen's Road 49 100% Lugard Road to end Renewal £44,201.81 £1,598,336.89
2025 U1552/005 Burrows Mews Borough and Bankside 84 95% Ufford Street to end towards north Renewal £47,429.91 £1,645,766.80
2025 U0484/005 Camberwell Stat Rd Camberwell Green 53 100% Camberwell New Road to Knatchbull Road Renewal  £70,125.61 £1,715,892.41
2025 U0640/005 Churchyard Row St George's 133 100% Newington Butts to Longville Road Renewal  £92,052.07 £1,807,944.48
2025 U0690/005 Collinson Street Borough and Bankside 38 90% Southwark Bridge Road to end Renewal £53,835.12 £1,861,779.60
2025 U1561/005 Flockton Street North Bermondsey 50 100% George Row to end Structural Surface  £16,993.46 £1,878,773.06
2025 U0296/010 Gibbon Road Nunhead and Queen's Rd 141 100% Senate Street to Kimberley Avenue Renewal  £151,685.50 £2,030,458.56
2025 U0140/015 Gilkes Crescent Dulwich Village 30 11% Carlton Avenue to End Structural Surface  £20,114.40 £2,050,572.96
2025 U1028/005 Lockyer Street London Bridge and West Bermondsey 44 100% Kipling Street to End Thin Surface  £11,473.57 £2,062,046.53
2025 U1044/005 Melior Street London Bridge and West Bermondsey 98 100% Weston Street to end Renewal  £53,314.86 £2,115,361.39
2025 U0763/005 New Globe Walk Borough and Bankside 113 100% Park Street to Bankside Renewal  £123,688.21 £2,239,049.60
2025 U0759/005 Porter Street Borough and Bankside 81 100% Park Street to end Renewal  £43,609.00 £2,282,658.60
2025 U0721/015 Redcross Way Borough and Bankside 83 100% Southwark Street to Park Street Renewal  £88,738.24 £2,371,396.84
2025 U1318/005 Ruby Triangle Old Kent Road 92 55% Sandgate Street to end Renewal  £49,041.27 £2,420,438.11
2025 U0684/005 Rushworth Street St George's 68 100% King James Street to Webber Street Renewal  £37,470.76 £2,457,908.87
2025 U5064/005 Sam King Walk Camberwell Green 59 100% Edmund St to Chiswell St Renewal  £31,871.43 £2,489,780.30
2025 U0351/005 Scylla Road Rye Lane 82 100% Consort Road to end Renewal  £98,366.25 £2,588,146.55
2025 U1534/005 Shards Square Old Kent Road 24 83% Peckham Park Rd to end towards south east Renewal  £16,000.39 £2,604,146.93
2025 U1532/005 Tarn Street Chaucer 31 100% Rockingham Street to end towards north east Renewal  £54,545.99 £2,658,692.93
2025 U0483/005 Warner Road Camberwell Green 99 100% Denmark Road to Lowth Road Renewal  £111,610.13 £2,770,303.05
2025 U0483/010 Warner Road Camberwell Green 72 100% Lowth Road to Crawford Road Renewal  £76,335.57 £2,846,638.62
  Total £2,846,638.62
Proposed footway maintenance programme for 2025 to 2026 (preventative work with capital spend)
Year Road class Road  Ward Treated length (metres) Treated length (%) Section description Treatment description Cost whole scheme Cumulative cost
2025 B202 Abbey Street London Bridge and West Bermondsey 10 2% Jamaica Road to Tower Bridge Road Patching £1,209.96 £1,209.96
2025 U1095/005 Avondale Square Old Kent Road 62 100% 65m From J/W Old Kent Rd Is PH Reconstruction>Renewal £6,963.29 £8,173.25
2025 U1095/005 Avondale Square Old Kent Road 62 100% 65m From J/W Old Kent Rd Is PH Reconstruction>Renewal £6,963.29 £15,136.53
2025 U0894/005 Aylesbury Road Faraday 120 79% Villa Street to Dawes Street Reconstruction>Renewal £13,444.80 £28,581.33
2025 U0894/005 Aylesbury Road Faraday 130 86% Villa Street to Dawes Street Reconstruction>Renewal £14,565.20 £43,146.53
2025 PL05_/005 Barnards Wharf Surrey Docks 122 72% Barnard's Wharf (north to south) Reconstruction>Renewal £24,555.58 £67,702.11
2025 PL05_/005 Barnards Wharf Surrey Docks 107 64% Barnard's Wharf (north to south) Reconstruction>Renewal £21,530.50 £89,232.62
2025 PL05_/005 Barnards Wharf Surrey Docks 100 60% Barnard's Wharf (north to south) Reconstruction>Renewal £44,218.38 £133,451.00
2025 U0190/010 Basingdon Way Champion Hill 10 16% Basingdon Way roundabout to end towards south west Patching £1,209.96 £134,660.96
2025 U0938/005 Beckway Street North Walworth 22 26% East Street to End Patching £2,649.81 £137,310.77
2025 C21 Bellenden Road Rye Lane 111 25% Oxenford Street to Maxted Road Reconstruction>Renewal £20,778.88 £158,089.65
2025 C21 Bellenden Road Rye Lane 138 17% Maxted Road to Peckham High Street Reconstruction>Renewal £27,860.99 £185,950.64
2025 C21 Bellenden Road Rye Lane 178 21% Maxted Road to Peckham High Street Reconstruction>Renewal £35,835.10 £221,785.74
2025 C21 Bellenden Road Rye Lane 178 21% Maxted Road to Peckham High Street Reconstruction>Renewal £35,835.10 £257,620.83
2025 A2205 Bermondsey Street London Bridge and West Bermondsey 311 60% Long Lane to Crucifix LN/ST. Thomas Street Resurface>Reflag £31,402.35 £289,023.18
2025 A2205 Bermondsey Street London Bridge and West Bermondsey 237 46% Long Lane to Crucifix LN/ST. Thomas Street Resurface>Reflag £23,929.39 £312,952.57
2025 U1232/010 Bevington Street North Bermondsey 156 94% Scott Lidgett Crescent to Chambers Street Reconstruction>Renewal £46,668.47 £359,621.04
2025 A3202 Borough Road St George's 173 54% Southwark Bridge Road to London Road Resurface>Reflag £102,245.30 £461,866.34
2025 A215 Camberwell Road North Walworth 102 9% Westmoreland St to Elephant & Castle roundabout (Walworth Rd) Reconstruction>Renewal £35,287.11 £497,153.45
2025 A215 Camberwell Road North Walworth 178 16% Westmoreland St to Elephant & Castle roundabout (Walworth Rd) Reconstruction>Renewal £82,697.12 £579,850.56
2025 A215 Camberwell Road North Walworth 153 14% Westmoreland St to Elephant & Castle roundabout (Walworth Rd) Resurface>Reflag £36,307.37 £616,157.94
2025 A215 Camberwell Road North Walworth 141 13% Westmoreland St to Elephant & Castle roundabout (Walworth Rd) Resurface>Reflag £29,259.05 £645,416.99
2025 U0818/005 Chandler Way Peckham 113 100% Diamond Street to Lidgate Road Resurface>Reflag £11,352.12 £656,769.10
2025 U2087/005 Chapel Court Chaucer 84 96% Footpath off Borough High Street Reconstruction>Renewal £16,910.20 £673,679.30
2025 U0290/005 Cheam Street Nunhead and Queen's Road 33 100% Evelina Road to end Reconstruction>Renewal £6,331.16 £680,010.46
2025 U0389/005 Choumert Road Rye Lane 158 100% Rye Lane to Choumert Grove Resurface>Reflag £8,853.40 £688,863.86
2025 U0389/005 Choumert Road Rye Lane 158 100% Rye Lane to Choumert Grove Reconstruction>Renewal £17,706.80 £706,570.66
2025 U0153/005 Colwell Road Goose Green 106 96% Lordship Lane to Playfield Crescent Reconstruction>Renewal £16,578.11 £723,148.77
2025 U0153/010 Colwell Road Goose Green 60 100% Playfield Crescent to Melbourne Grove Reconstruction>Renewal £7,376.15 £730,524.92
2025 C15 Cooks Road Newington 132 40% Hillingdon Street to Westcott Road Resurface>Reflag £15,096.05 £745,620.97
2025 C15 Cooks Road Newington 233 70% Hillingdon Street to Westcott Road Reconstruction>Renewal £55,905.20 £801,526.17
2025 U0285/010 Daniels Road Nunhead and Queen's Road 116 59% Tappesfield Road to Linden Grove Reconstruction>Renewal £23,367.73 £824,893.90
2025 U0219/015 Edgar Kail Way Champion Hill 10 9% Carriage Way from north east to end towards south west Patching £1,209.96 £826,103.86
2025 U0416/005 Elm Grove Rye Lane 20 6% Highshore Road to end Patching £2,419.92 £828,523.78
2025 U0394/005 Everthorpe Road Rye Lane 120 100% Oglander Road to Oxenford Street Reconstruction>Renewal £21,245.42 £849,769.20
2025 U0107/005 Fellbrigg Road Goose Green 10 4% Whateley Road to North Cross Road Patching £1,209.96 £850,979.16
2025 U1561/005 Flockton Street North Bermondsey 53 100% George Row to end Reconstruction>Renewal £5,941.48 £856,920.64
2025 U0086/035 Friern Road Dulwich Hill 101 84% Upland Road to Peckham Rye Reconstruction>Renewal £25,488.82 £882,409.46
2025 U0086/035 Friern Road Dulwich Hill 117 98% Upland Road to Peckham Rye Reconstruction>Renewal £25,227.37 £907,636.83
2025 U0608/010 Gateway Faraday 53 100% Gateway House No:25 to Walworth Road Reconstruction>Renewal £14,438.87 £922,075.71
2025 U0784/005 Gatonby Street Peckham 46 107% Watts Street to Corbden Close Resurface>Reflag £2,578.60 £924,654.31
2025 U0210/005 Green Dale Goose Green 106 91% East Dulwich Grove to end towards north east Reconstruction>Renewal £27,905.58 £952,559.89
2025 U0210/005 Green Dale Goose Green 102 88% East Dulwich Grove to end towards north east Reconstruction>Renewal £28,209.88 £980,769.77
2025 B240 Harper Road Chaucer 210 32% Falmouth Road to  New Kent Rd Reconstruction>Renewal £121,344.64 £1,102,114.41
2025 U0658/005 Keyworth Street St George's 201 71% Borough Road to Southwark Bridge Road Reconstruction>Renewal £40,534.06 £1,142,648.46
2025 U0658/005 Keyworth Street St George's 116 41% Borough Road to Southwark Bridge Road Reconstruction>Renewal £23,434.29 £1,166,082.75
2025 U1212/015 Lafone Street North Bermondsey 100 89% Gainsford Street to Shad Thames Reconstruction>Renewal £11,204.00 £1,177,286.75
2025 U0935/005 Larissa Street North Walworth 40 98% Elsted Street to Tisdall Place Reconstruction>Renewal £8,034.61 £1,185,321.36
2025 U0584/005 Lorrimore Square Newington 166 63% Chapter Road, house No:1 to Chapter Road, house No:64 Resurface>Reflag £16,189.39 £1,201,510.75
2025 U0942/005 Massinger Street North Walworth 10 13% Old Kent Road to Congreve Street Patching £1,209.96 £1,202,720.71
2025 U0986/005 Merrick Square Chaucer 103 55% Trinity Street to Trinity Church Square Reconstruction>Renewal £20,679.45 £1,223,400.16
2025 U0867/010 Merrow Street Faraday 175 72% Portland Street to end Reconstruction>Renewal £35,361.17 £1,258,761.33
2025 U0867/010 Merrow Street Faraday 123 51% Portland Street to end Reconstruction>Renewal £24,827.84 £1,283,589.17
2025 U0867/010 Merrow Street Faraday 120 49% Portland Street to end Resurface>Reflag £12,102.34 £1,295,691.50
2025 U0867/010 Merrow Street Faraday 115 47% Portland Street to end Resurface>Reflag £11,586.06 £1,307,277.56
2025 U0867/005 Merrow Street Faraday 154 51% Walworth Road to Portland Street Reconstruction>Renewal £31,109.92 £1,338,387.48
2025 U0867/005 Merrow Street Faraday 154 51% Walworth Road to Portland Street Reconstruction>Renewal £31,109.92 £1,369,497.40
2025 U0867/005 Merrow Street Faraday 157 52% Walworth Road to Portland Street Reconstruction>Renewal £31,702.84 £1,401,200.24
2025 U0867/005 Merrow Street Faraday 118 39% Walworth Road to Portland Street Reconstruction>Renewal £23,704.53 £1,424,904.77
2025 B238 Peckham Rye Dulwich Hill 561 100% St Aidans Road to Barry Road Reconstruction>Renewal £144,935.65 £1,569,840.42
2025 B219 Peckham Rye Peckham Rye 126 34% Barry Road to East Dulwich Road Reconstruction>Renewal £22,309.57 £1,592,149.99
2025 B238 Peckham Rye Dulwich Hill 369 66% St Aidans Road to Barry Road Reconstruction>Renewal £88,275.39 £1,680,425.38
2025 U0544/005 Redcar Street Camberwell Green 127 100% Comber Grove to Councillor Street Reconstruction>Renewal £14,240.28 £1,694,665.67
2025 U1164/015 Rouel Road South Bermondsey 110 43% Lucey Road to Old Jamaica Road Reconstruction>Renewal £22,157.70 £1,716,823.37
2025 U1218/010 Shad Thames North Bermondsey 140 42% Maguire Street to Jamaica Road Reconstruction>Renewal £28,226.01 £1,745,049.38
2025 U1218/005 Shad Thames North Bermondsey 210 65% Tower Bridge Road to Maguire Street Reconstruction>Renewal £23,528.40 £1,768,577.78
2025 U1218/005 Shad Thames North Bermondsey 200 62% Tower Bridge Road to Maguire Street Reconstruction>Renewal £22,408.00 £1,790,985.78
2025 U0347/005 Sturdy Road Rye Lane 107 100% Consort Road to Gordon Road Reconstruction>Renewal £15,805.24 £1,806,791.02
2025 U0757/005 Thrale Street Borough and Bankside 142 84% Southwark Street to Southwark Bridge Road Resurface>Reflag £13,197.98 £1,819,989.00
2025 B300 Union Street Borough and Bankside 185 47% Southwark Bridge Road to Great Suffolk Street Resurface>Reflag £32,994.10 £1,852,983.10

Street works

Our network management team co-ordinate roadworks and street works activities. 

We carry out daily, detailed checks on the street works permit system to both manage permit applications and assess their impact on roads in Southwark and neighbouring boroughs. As well as roads and street works permits, we also co-ordinate all licensable activities and events in the borough.

In addition to the daily checks, we hold quarterly meetings to forward plan major works with:

  • the main six utility companies
  • anyone who wants to undertake major works in the borough
  • our own own highways officers (maintenance and projects) 

Climate change, resilience and adaptation 

Like many councils, Southwark has declared a climate emergency. We are working to become carbon net zero by 2030 and are developing a carbon assessment tool to use on all our projects. 

The estimated carbon emissions can be established and then the scheme can be amended to achieve a 25% reduction in emissions, either by using less carbon intensive materials and construction practices, or by influencing the transport use of the highway to encourage more sustainable transport. 

Climate change and Streets for People

We have also implemented our Streets for People strategy which includes:

  • more tree planting
  • more planting beds for biodiversity
  • wider pavements and cycle routes to encourage active travel

Streets for People schemes, representing a £2 million investment for 2025 to 2026, are being proposed in:

  • Bermondsey Street
  • America Street
  • Great Suffolk Street
  • Stoney Street
  • Cooks Road
  • Red Post Hill
  • Iliffe Street
  • Rye Lane
  • Dulwich Village 
Climate change and flood prevention

Climate change will probably bring more rainfall in London because more moisture can be held in warmer air. For Southwark, this risks more flooding. Creating areas to store rainwater helps to reduce flooding in low areas and stops sewers overflowing. Last year we invested £2,812,657 in flood prevention measures such as the Lost Peck River scheme and Astley House sustainable urban drainage scheme. 

This year, we will work on flood prevention schemes in Belair Park, Deal Porters Walk and Russia Dock Woodland.

Additional information on plans 

We are investing significant capital expenditure in active travel. This includes:

  • spending approximately £750k in creating more cyclehangers for the secure storage of bicycles, and on bus priority measure
  • spending another £331k in the creation of more cycleways through Borough Road, Tanner Street, Lower Road and Burgess Park
  • planned spend of £166k on school streets.

Our Streets for People Strategy represents a significant £13.9m additional investment in delivering improvements to our public realm over the next ten years. Read more about our current Streets for People projects