Southwark Regeneration in Partnership Programme

Manor Place Terrace SE17

Manor place terrace
Manor Place

Proposed development

Project details

Redevelopment of the site to include 56 residential units (use class C3), a 757sqm Health Centre (Use Class D1), 70sqm pharmacy (use class A2), 261sqm café (Use class A3) and 45sqm retail unit (use class A1) in a part 3, part 4 and part 5 & part 6 storey block, including retention of the existing terrace façade along Manor Place.

Improved entrance to Pasley Park associated landscaping and public realm improvements will also take place. Please note all areas given are approximate and subject to change. Demolition of single storey office building and a derelict three-storey row of shops and flats above (with the retention of the original three-storey Victorian facade), and the construction of a six storey building (behind retained façade) comprising of the following:

  • 56 flats (20 x social rented, 8 x intermediate and 28 x private)
  • a health centre/office space (745sqm)
  • (use Class D1/B1), pharmacy/shop (85sqm)
  • (use Class A1) and cafe (285sqm) (use Class A3)
  • associated landscaping and public realm works

Unit size Number of units Percentage

One bedroom 14 - 25%
Two bedroom 25 - 45%
Three bedroom 17 - 30%
Total 56 - 100%

Planning Status: Application 17/AP/0907 for: Full Planning Application. Planning obtained.

The Façade is to be retained and the rest of the building will be demolished.

Durkan Ltd have been awarded the contract to deliver both Braganza Street and Manor Place schemes and will start on site, strengthening the façade of Manor Place in November 2019 with an aim to complete both sites by Winter 2021.

Page last updated: 03 October 2019