Full plans application

A Full Plans application may be submitted for any building work but must be submitted for large buildings, schools, shops, offices, railway premises, factories and hotels. Unless you have a thorough knowledge of the regulations and building construction in general, it's advisable to seek professional assistance.

A full plans application is broken into a plan assessment stage and a site inspection stage.

Plan assessment

  1. Complete the full plans application form and submit detailed plans or drawings before work commences.
  2. A plan checking officer will then check your plans or drawings to make sure that they comply with the building regulations.
  3. We may need to write to you to ensure compliance, before issuing an approval notice.

Site inspection

  1. A building control officer visits the building works site at regular intervals to make sure that the work in progress conforms with the building regulations.
  2. It is important to note that your building works must reflect the plans that have been approved by your plan checking officer in the plan assessment stage.
  3. After work has started and a first inspection has been undertaken you will be invoiced for the building control inspection charge.
  4. Once your plans and the final inspection prove that you have complied with the building regulations, Southwark building control will issue you a completion certificate.