Roads around Borough Market
Information about our current programme of works close to Borough Market
On this page you can read about our current schemes that are close to Borough Market.
Bedale Street road safety scheme
What is proposed
This scheme includes:
- pavement widening
- raised crossings
- safety bollards
Loading bays will be relocated onto streets around Borough Market and disabled parking bays will be relocated to Park Street.
If this scheme goes ahead, it will be a trial at first.
What stage we are at
Following a public consultation, recommendations are currently being made to the Cabinet Member for Clean Air, Streets and Waste. If these recommendations are approved the scheme will be built in November 2025.
Stoney Street public realm
What is proposed
This scheme includes:
- raising the road to pavement level
- resurfacing the road in quality materials
- replacing the concrete blocks with strong security bollards
We will not be changing the current road-closure timings (10am to midnight).
What stage we are at
We are consulting on this scheme now as part of our Streets for People London Bridge-area engagement.
Following the consultation, a recommendation will be made to the Cabinet Member for Clean Air and Waste. If the recommendation is to proceed with the scheme, it will start in early 2026.
Road resurfacing
What is proposed
The following roads need resurfacing:
- Park Street junction with Redcross Way
- Stoney Street (Park Street to Winchester Walk)
- Winchester Walk and Redcross Way
What stage we are at
This road resurfacing work will be done at the same time as the Stoney Street public realm work in early 2026.
Holistic approach
We are not just looking at the roads around Borough Market. We are also considering the impact of trading licenses and pedestrian flow in the area. We are working in partnership with Borough Market, residents and stakeholders.
What stage we are at
Following a meeting on 10 September 2025, an action plan is being written to address the issues raised. This will be shared with those who attended the meeting. Quarterly meetings will be scheduled with stakeholders.
Contact us
If you have any questions about the above schemes, please email the team on StoneyStreet@southwark.gov.uk